Pitch equals takt time times pack-out quantity.

Study for the Lean Bronze Certification Exam with flashcards and multiple-choice questions. Each question comes with hints and explanations. Prepare thoroughly for your certification journey!

Multiple Choice

Pitch equals takt time times pack-out quantity.

Explanation:
The thing being tested is how pacing, takt time, and pack size relate to the schedule of starting new packs. Takt time is the pace at which you must complete units to meet demand. If you package units in batches (pack-out quantity), the time between starting each new pack must expand by how many units you’re delivering in each pack, so you keep the same overall flow rate. That’s why pitch equals takt time times pack-out quantity. If one unit must be produced every takt time, a pack of several units requires starting a new pack after that many takt times equal to the number of units in the pack. For example, with a takt time of 60 seconds and a pack-out quantity of 2, you start a new pack every 120 seconds, delivering 2 units each time and maintaining the required throughput of 60 units per hour. The other forms don’t align with how the pace works: adding, dividing, or taking the reciprocal would not produce the correct interval between pack starts to sustain the demand rate.

The thing being tested is how pacing, takt time, and pack size relate to the schedule of starting new packs. Takt time is the pace at which you must complete units to meet demand. If you package units in batches (pack-out quantity), the time between starting each new pack must expand by how many units you’re delivering in each pack, so you keep the same overall flow rate.

That’s why pitch equals takt time times pack-out quantity. If one unit must be produced every takt time, a pack of several units requires starting a new pack after that many takt times equal to the number of units in the pack. For example, with a takt time of 60 seconds and a pack-out quantity of 2, you start a new pack every 120 seconds, delivering 2 units each time and maintaining the required throughput of 60 units per hour.

The other forms don’t align with how the pace works: adding, dividing, or taking the reciprocal would not produce the correct interval between pack starts to sustain the demand rate.